Nolan Park Site Preparation

IMG_2293

With the Deep Services complete we’re taking advantage of the good weather and prepping roads to pave and grading the site for the shallow utilities install. Next week we’ll start excavation and forming of building foundations. Please see a few site pictures below;

Construction at Cranston Ridge 3

We’re pleased to announce that the roof is on and shingled at Cranston Ridge Building 3! With the roof in place and the exterior finishes starting, we are moving forward with insulation and drywall on the main floor while continuing the rough in work and fire rating on the upper floors. There is also good progress on Read More

Auburn Walk 2 Parkade Pour

We’re happy to have the parkade under building 2 substantially complete! Earlier this week we poured the last portion of the suspended and framing will be underway next week! Please see a few progress pictures of the construction to date;        

Nolan Park Deep Services

We’ve got equipment on site and we’re thrilled to have the sites Deep Services started. There will be a lot of activity on the site over the next few weeks as the water lines, storm and sewer pipe are installed. Please see some pictures below of the activity.  

Excavating Building 3

We’re excited to have started the excavation of Building 3, there is a lot of rock to deal with but after long search we found a place to take it. Please see a few pictures of our progress and of the site.      

Framing Building 3

Framing of Building 3 started in August and we’re excited with the progress to date. Currently the 4th floor is being framed with roof trusses coming next week. The rough-in of the mechanical and electrical is also underway in the building and on the outside the ramp has been poured and the tunnel connection is being Read More

Underway At Auburn Walk

Construction at Auburn Walk started this summer and we’re well underway! Currently we’re working on the parkade, prepping for the slab on grade pour and we also put the first lift of pavement down for the site roads. Please check out some pictures below.    

Happy New Years!

We hope everyone had a happy and safe holiday, we feel refreshed and are happy to be back at it. On building 1 the framing of the roof is wrapping up early next week and the roofing will follow, inside the building rough-ins of mechanical and electrical systems continue throughout. Preparation for the delivery of Read More